Solar park La Solana (Spain)
Operator:                           La Solana Solar Servicios 
                                             Generales, A.I.E.
Energy company:             Union Fenosa
Location:                            Castilla La Mancha, Spain
Commissioning date:      March 2008 
Completion time:              26 weeks
Rated system power:      6,530 KWp
Solar park Miegersbach
Operator:                            LADIT Mobiliengesellschaft mbH & Co. KG 
                                              an investment company of KGAL
Energy company:              E.ON
Location:                             Miegersbach, Germany
Commissioning date:      July 2005
Completion time:              33 weeks 
Rated system power:      5,300 KWp
Solar park Malching
Operator:                             LEMARI Mobilienverwaltungs GmbH
Energy company:               Stadtwerke Fürstenfeldbruck
Location:                              Malching, Germany
Commissioning date:       July 2009 
Completion time:               8 weeks
Rated system power:       4,732 KWp
Solar Park Red
Operator:                             Consensus Business Group
Energy company:               RWE Rhein-Ruhr
Location:                              Longuich
Commissioning date:       September 2007
Completion time:               12 weeks
Rated system power:       3,162 KWp
Solar park Rickelshausen
Operator:                           GLS Energie AG
Energy company:             Thüga AG E-Werk Singen
Location:                            Rickelshausen, Germany
Commissioning date:      July 2007
Completion time:             10 weeks
Rated system power:     1,124 KWp
Solar park Haimhausen
Operator:                            Kommunalunternehmen 
                                              E.ON Bayern AG
Location:                             Haimhausen, Germany
Commissioning date:      July 2006
Completion period:          11 weeks
Rated system power:      1,120 KWp
Solar park Pontoirakleia (Greece)
Energy company:              D.E.I
Location:                             Pontoirakleia/Kilkis, 
                                              Greece
Commissioning date:      July 2008
Completion time:              18 weeks
Rated system power:      943 KWp